Project update - August 2025

Works are progressing on site to construct the battery and substation areas.

 Construction activities that are ongoing or will commence over the next few months include:

  • Earthworks and the installation of bored (drilled) piles, including the use of excavators, earth moving equipment and a piling rig

  • Installing steel reinforcement and pouring concrete to construct the benches that battery units and support facilities (like the substation) will be mounted on

  • Delivery of equipment and materials

  • Installation of electrical infrastructure

  • Delivery of oversize battery and substation components is expected to start from October 2025. Further notification will be provided before this commences. 

Previous
Previous

join our Community Benefit Committee

Next
Next

Project update - April 2025